Service

Change Search Parameters

Select Searchorder

Select Country

Austria Belgium Bulgaria Cyprus Czech Republic Germany Denmark Estonia Spain Finland France United Kingdom Greece Hungary Ireland Italy Malta Netherlands Lithuania Luxemburg Lativia Poland Portugal Romania Sweden Slovenia Slovakia
AT
BE
BG
CY
CZ
DE
DK
EE
ES
FI
FR
GB
GR
HU
IE
IT
MT
NL
LT
LU
LV
PL
PT
RO
SE
SI
SK

Select Hot Topics

Financing and Management

Funding Incentives Project Management Asset Management

Knowledge and Support

Partnership Working Work with Residents Capacity Building

Architecture

Thermal Insulation Windows and Shading Air Tightness Environmental Design

Renewable Energies

Solar Thermal Solar Photovoltaic Other Renewables

Building Services

Heating and Hot Water Cooling Ventilation Electricity Saving Products Water Saving

Monitoring and Certification

Certification Monitoring

Select Type of Project

Construction Refurbishment Other

Case Study: nZEC - Energy refurbishment of 191 dwellings in Zirkusgasse, Vienna, Austria (UNDER MONITORING)

Name of organisation: BWSG - Gemeinnützige Allgemeine Bau Wohn und Siedlungsgenossenschaft

Stage of development: completed

Year of finalization: 2012

Type of project: refurbishment

Area: urban

Scale: individual buildings

Type of building: Apartment in a block of six to ten stories

Number of units/dwellings: 191

Tenure:

Street: Zirkusgasse, 47

Postcode: 1020

City: Wien

Region/ County:

Country: Austria

Last Update: 17.04.2015

Funding Certification Monitoring Thermal Insulation Heating and Hot Water

Short Description

This renovation project demonstrates the whole range of modernisation measures which might be required in older buildings.

The rental building was built in 1951/52 - after a bomb had turned down the existing older building - at a very poor quality level. There were very small dwellings lacking a central heating system. No elevators were built in. It was necessary to plan a deep renovation to bring the building/dwellings to a standard which would ensure a future use. Due to its central location and attractive inner courtyard the building also bore the opportunity of densification. Nevertheless the project was a complex challenge.

Since the construction of the existing staircase did not allow a barrier-free construction of elevator it had to replaced (while residents stayed in their dwellings!). Modernisation measures in single dwellings were realised in vacant dwellings (67); these measures comprised the re-shaping and merging of existing dwellings to get bigger apartments with better situation and modern amenities.

The building was connected to the district heating. Balconies were added on. In the roof 32 new dwellings were built in. The whole building was insulated and all windows were replaced to obtain low energy level.


Key Elements

Certification

Calculated heating demand for space heating:

  • before renovation 121 kWH/m2 (gross)
  • after renovation 33,7 kWh (gross)


     

Thermal Insulation

Insulation of façade by thermal insulation compound system with EPS.


Heating and Hot Water

District heating for dwellings which were modernized.


Funding

Mix of own funds and public soft loans. Overall cost of the project: € 17.730.000.


Monitoring

Click here to access the monitoring data on the HIVE Database!


Main Results

The project is an example of “very deep” renovation for older buildings, where many aspects play a role: size of dwellings, lack of basic amenities. It also demonstrates the high costs of such measures, where energetic aspects are not the sole ones.


Lessons learned

The project shows that it is possible to realize deep renovation in buildings even when residents stay in their dwellings.


Additional Information

Ms Eva Bauer
Gbv - The Austrian Federation of Limited Profit Housing Associations